Bavaro Hall – Work Continues
By Luke | November 24, 2009
This is a short work week with Thanksgiving coming, but work continues on Bavaro Hall. On the exterior work continues on the detail trim work and on installing the large arching windows. Work has also begun on the final brick work leading to the roof at each end of the building. Inside work continues on installing the dry wall.




Topics: Bavaro Progress | Comments Off
Work Begins on the Details
By Luke | November 18, 2009
The brick work on the main exterior walls is now complete and the focus of the work is now on the detail brick around the entrances as well as on the cast stone and granite details. Work also continues on the large windows and on the roofing trim. Inside extensive work is being done on the drywall which is targeted to be finished by the end of this month. Work is also nearing completion on the south stairs in the building and then work will begin on the north stairs.




Topics: Bavaro Progress | Comments Off
Bricks Have Reached the Roof
By Luke | November 9, 2009
Viewing this week’s Bavaro pictures reveals that the exterior brick work has reached the roof trim line on the east side of the building. Work also continues on the east side installing the large window sections and on adding the trim to the windows on the west side of the building. Inside the major activity is installing the drywall. Finally, the utility work that has been blocking the fire exit in the southwest corner of Ruffner is nearly complete.






Topics: Bavaro Progress | Comments Off
Construction as Usual
By Luke | November 3, 2009
This week work continues on the exterior with the brick work continuing around the top floor. Work also continues on the roof trim. This week’s pictures also show work beginning on the main windows on the east side of the building and on installation of windows on the west side of the building facing the courtyard connecting to Ruffner. Not visible in the pictures is the drywall work which is now in full swing on all floors.




Topics: Bavaro Progress | Comments Off
One Floor To Go!
By Luke | October 26, 2009
This week the brick work moves to the last floor. The first photo shows Bavaro Hall looking from north. You can see the brick work appoaching the last floor as well as the continuing work on the roof trim, which is highlighted in the second photo. The last two photos show Bavaro Hall looking from the south and the west. Work continues inside on the rough-ins and on installing dry wall on the ground floor.




Topics: Bavaro Progress | Comments Off
Bavaro Hall Construction 62% Complete
By Luke | October 19, 2009
This month’s construction report indicates that Bavaro Hall is now 62% complete. The exterior brick work has made great gains this past week with work on the east side now beginning on the fourth floor. Work on the exterior also continues on the roof trim details and on framing the large window openings. Internal work continues on framing, utility rough-ins, and in some areas work as begun on installing the drywall.




Topics: Bavaro Progress | Comments Off
A Peek Inside Bavaro Hall
By Luke | October 13, 2009
This week I have posted a few pictures of the inside of Bavaro Hall provided by the Curry School’s Foundation photographer. I have also included the traditional views of the outside of the building from the north, east, and south. These pictures show that a lot of progress was made this past week on the exterior brick work.








Topics: Bavaro Progress | Comments Off
The Bricks Keep On Climbing
By Luke | October 6, 2009
This week’s pictures show that work continues on the brick exterior work. The first picture shows the view of Bavaro Hall looking from the north. The next picture shows a close-up of the brick work on the ground and first floors. The third picture shows the east side of Bavaro and the last picture shows the view from the south. Work on the rough-ins continues on the interior.




Topics: Bavaro Progress | Comments Off
Construction on Schedule
By Luke | September 28, 2009
Work continues this week on the rough-ins on the interior and on the brick work on the outside. The building is almost weathered in now that most of the windows have been installed. Soon work will begin on installing the interior walls. Work also continues on the roof trim around the top of the building.






Topics: Bavaro Progress | Comments Off
Bonnycastle Drive Reduced to One Lane
By Luke | September 21, 2009
This week between September 22nd and September 25th barricades will be installed and Bonnycastle Drive will be reduced to one lane of traffic. During this time, utility connections will be made. Access will still be maintained to the R-1 parking lot. Meanwhile, construction continues on schedule with electrical and plumbing rough-ins being performed on the inside and brickwork and work on the roof trim continuing on the outside.




Topics: Bavaro Progress | Comments Off
« Previous Entries